PENGENDALIAN WAKTU DAN BIAYA STRUKTUR JEMBATAN OVERPASS DI PROYEK JALAN TOL CISUMDAWU SUMEDANG SEKSI 5A DENGAN METODE EARNED VALUE (STA.42+345)

Purwanti, Winda (2022) PENGENDALIAN WAKTU DAN BIAYA STRUKTUR JEMBATAN OVERPASS DI PROYEK JALAN TOL CISUMDAWU SUMEDANG SEKSI 5A DENGAN METODE EARNED VALUE (STA.42+345). Sarjana (S1) thesis, Universitas Islam “45” Bekasi.

[img] Text
PENGENDALIAN WAKTU DAN BIAYA STRUKTUR JEMBATAN OVERPASS DI PROYEK JALAN TOL CISUMDAWU SUMEDANG SEKSI 5A DENGAN METODE EARNED VALUE.pdf

Download (991kB)
[img] Text
BAB I.pdf

Download (103kB)
[img] Text
BAB II.pdf
Restricted to Repository staff only

Download (555kB) | Request a copy
[img] Text
BAB III.pdf
Restricted to Repository staff only

Download (382kB) | Request a copy
[img] Text
BAB IV.pdf
Restricted to Repository staff only

Download (982kB) | Request a copy
[img] Text
BAB V.pdf

Download (94kB)
[img] Text
DAFTAR PUSTAKA.pdf

Download (31kB)

Abstract

The Section 5A Cisumdawu Sumedang Toll Road project, especially the Sta.42+345 Overpass Bridge work, experienced delays starting from the mini pile piling work. This study uses the Earned Value method obtained to determine job performance regarding time and cost. The data used are the master schedule, detailed schedule, weekly project reports to obtain PV (Planned Value) and EV (Earned Value), and interviews to determine factors that can affect time performance. From the analysis, it was found that the Concept Value of Results in the 68th week with a planned cost estimate (BCWS) of Rp. 4,005,050,712,657, the value of completion of work in the field (BCWP) is Rp. 664,738,707.50 and the value of the actual costs that have been issued in the field (ACWP) is Rp. 738,598,563.88 from the value of the three indicators which is greater than the total budget is Rp. 103,865,000,000.00. Judging from the cost variance (CV) the project suffered a loss of -Rp. 73,859,856.39 of the total budget of Rp. 103,865,000,000.00. or 10% of the total budget, represented by the Cost Performance Index (CPI)<1. Meanwhile, from the aspect of the project schedule, there was an increase in time from the planned schedule of 500 days (8 months) to 872 days as indicated by the Time Performance Index (SPI) value, which was <1 meaning that the work was completed longer than the planning schedule.

Item Type: Thesis (TA, Skripsi, Tesis, Disertasi) (Sarjana (S1))
Contributors/Dosen Pembimbing,NIDN Dosen bisa diakses di LINK https://bit.ly/NIDNdosenunismabekasi:
ContributionContributors / Dosen PembimbingNIDN
UNSPECIFIEDSylviana, Rika0423096804
UNSPECIFIEDParyati, Ninik0429017903
Keywords / Kata Kunci: earned value, pengendalian waktu biaya, jembatan overpass.
Subjects: Manajemen Konstruksi
Faculty: Fakultas Teknik > Teknik Sipil S1
Depositing User: Ms winda purwanti
Date Deposited: 23 Feb 2024 07:21
Last Modified: 23 Feb 2024 07:21
URI: http://repository.unismabekasi.ac.id/id/eprint/2280

Actions (login required)

View Item View Item